PERI GmbH is building the first 3D printed residential building in Germany, and precisely in Beckum, North Rhine-Westphalia. The two-story detached house with approx. 80 sqm of living space per floor is being built with a COBOD system that PERI uses to provide 3D printing construction services. This segment is booming way beyond anyone could have imaged (except us: three years ago, when only a handful of companies were active, we forecast a €40 billion dollar industry by 2027, among general skepticism)

This construction technique, which is being put into practice in Germany for the first time, has come through all of the regulatory approval processes over the last few weeks and months. The engineering office Schießl Gehlen Sodeikat supported the development of the concept for obtaining the approval, the planning and execution of the corresponding approval tests was carried out by the Technical University of Munich.The building was planned by MENSE-KORTE ingenieure+architekten and the client is Hous3Druck GmbH. The materials used to produce printable concrete are being sourced from HeidelbergCement.

The federal state of North Rhine-Westphalia is supporting the 3D construction printing project in Beckum as part of its “Innovatives Bauen” (innovative construction) development scheme. Today, Ina Scharrenbach, Minister for Regional Identity, Communities and Local Government, Building and Gender Equality in the federal state of North Rhine-Westphalia, was briefed on the current state of affairs at the construction site in Beckum.

PERI builds the first 3D printed residential building in Germany Construction 3D Printing The PERI construction site in Germany. Copyright: PERI GmbH

“North Rhine-Westphalia innovation for Germany: digital, dynamic, ready to print – these are our keywords for the future of construction. We are proud that the first house to be 3D printed is being built in our federal state. This makes North Rhine-Westphalia a pioneer for Germany. Not tomorrow, not some day, but today. The state government of North Rhine-Westphalia is providing specific support for investments in the innovation engine of construction: the 3D house is being subsidized with 200,000 euros. Further projects are in the printing loop,” explains Scharrenbach.

“The construction of the 3D printed residential building in Beckum is a milestone for 3D construction printing technology”, says Thomas Imbacher, Innovation & Marketing Director at PERI GmbH. “We are very confident that construction printing will become increasingly important in certain market segments over the coming years and has considerable potential. Other residential printing projects are now being drawn up in Germany. We are proud that PERI’s involvement in the project in Beckum has seen us become a pioneer and forerunner for this new construction technique.”

The PERI construction 3D printer. Copyright: PERI GmbH

“At PERI, we see ourselves as a leading innovator in our markets,” says Dr Fabian Kracht, Finance & Organisation Director and Spokesperson of the PERI Group management board. “Investing wisely in start-ups that are offering new solutions in our markets is another aspect of that. 3D printing is a business segment that has emerged from this investment portfolio and has now made its way onto the market. The success story in Beckum is validation that we have taken the right approach.”

“3D construction printing fundamentally changes the way we build and the process of residential construction. As this is the first building of its kind, we are making a point of printing at a slower rate than what is actually possible,” says Leonhard Braig, Production & Supply Chain Director at PERI GmbH. “We want to take the opportunity to gain further experience in day-to-day operations as this will help us to leverage the cost reduction potential of our technology to a greater extent in the next printing project.”

The building was planned by MENSE-KORTE ingenieure+architekten and the client is Hous3Druck GmbH. “The concrete printing process affords us, designers, a high degree of freedom when we are designing buildings. With conventional construction methods, this would only be possible at a great financial cost,” says architect Waldemar Korte, partner of the architectural practice MENSE-KORTE ingenieure+architekten in Beckum. “With our printed residential building in Beckum, we are demonstrating the potential of the construction printing process. It is a huge privilege for our team to realize the first 3D-printed residential construction project in Germany. We believe in the future viability of construction printing technology for the construction sector and already have other 3D printing projects on our radar.”

Manufacturing on Demand

Maximize the freedom of your product design, get your ideal realized with 3D printing and other cutting-edge technologies!

Get Quote

Printing technology and materials

PERI uses 3D printers of type BOD2 for printing. This printing technology comes from the Danish manufacturer COBOD. PERI acquired a stake in COBOD back in 2018. The BOD2 printer used in Beckum is a gantry printer, which means that the print head moves about 3 axes on a securely installed metallic frame. The benefit here is that the printer can move along its frame to any position within the construction and only needs to be calibrated once.

The “i.tech 3D” material used in the printing process was developed by HeidelbergCement specifically for 3D printing. Its properties are tailored to the specific requirements of 3D construction printing and it works perfectly with the BOD2 printer. This ensures that consistent progress is made throughout the construction project.

“We had an efficient and innovative collaboration with HeidelbergCement. They have been instrumental in clarifying all outstanding questions regarding construction methods and printing materials quickly and easily,” says Fabian Meyer-Brötz, Head of 3D Construction Printing at PERI.

The building consists of triple-skin cavity walls, which are filled with an insulating compound. During the printing process, the printer takes into account the pipes and connections for water, electricity, etc. that are to be laid at a later time. The BOD2 has been certified in such a way that it is possible to carry out work within the printing area while printing is in progress. This means that manual work, such as the installation of empty pipes and connections, can be easily integrated into the printing process.

Only two operators are required to run the printer. The print head and the print results are monitored by a camera. With a speed of 1 m/s, the BOD2 is currently the fastest 3D construction printer available on the market.

The BOD2 only takes around 5 minutes to complete 1m² of a double-skin wall.

 

 

 

You might also like:

ICON’s Project Olympus looks at 3D printed Moon habitats for NASA Artemis: Other firms have theorized the use of construction 3D printing for interplanetary habitats. The underlying idea is that human habitats need to be ready before humans get to a planet. So they need to be built automatically, by robots, 3D printers and 3D printing robots. Construction 3D printing pioneer Contour Crafting saw space habitats as one of the first applications for the technology that goes by the same name. Another pioneer in this field, D-Shape, worked with the ESA and Norman Fosters on 3D printed Lunar habitats (read more about this in our recent Aerospace AMFocus 2020 eBook). Other firms (such as Ai SpaceFactory) have presented 3D printed habitat projects for Mars colonization in a recent contest run by NASA.

* This article is reprinted from 3D Printing Media Network. If you are involved in infringement, please contact us to delete it.

Author: Davide Sher

Leave A Comment

Your email address will not be published. Required fields are marked *